Pressure building after water main repaired

Published 9:24 pm Friday, May 19, 2017

Water is again flowing through Vicksburg’s water lines.

Employees for Florence-based Hemphill Construction Co. completed repairs to a section of the city’s 36-inch waterline about 10 p.m. and turned the water system over to the city’s water treatment plant to begin moving water.

But city officials said it could be at least 24 hours before the water system is at full pressure, and it may take until the end of next week before a boil water notice that has been put in effect may be lifted.

Email newsletter signup

Sign up for The Vicksburg Post's free newsletters

Check which newsletters you would like to receive
  • Vicksburg News: Sent daily at 5 am
  • Vicksburg Sports: Sent daily at 10 am
  • Vicksburg Living: Sent on 15th of each month

The city has been without water since after 11 a.m. Wednesday when city workers discovered a leak in the main waterline. The leak forced employees at the city water treatment plant to shut down the plant’s main valve to prevent backflow into the system, cutting off the city’s main water supply.

City public works director Garnet Van Norman said the cause of the leak was a 20-inch butterfly valve installed when the line was built in 1967.

“Tonight we will start turning on our high service pumps; we will turn them on one at a time,” ESG project manager Eddie Busby said at a Friday afternoon press briefing. ESG operates the water plant under contract to the city.

“We will probably bring the pressure up to about 80 psi (pounds per square inch), and then I can turn another pump on after that and it will progressively get better.”

When the system starts coming back on line, he said, there will probably be low pressure for some time while the city opens fire hydrants to release air from the system.

“It’s going to be a slow process, and it will probably be 24 hours before the pressure will be up where it needs to be citywide,” Busby said.

“We have to get chlorine throughout the system, and I would say probably toward the end of the week before we could start drinking from the system,” he said.

Once the chlorine is added, he said, workers will have to take 40 samples a day from different areas on the water system for testing. The city must have good samples for two consecutive days before water in the system is declared safe to drink.

“We’re going to make sure the water is safe to drink,” Busby said.

Van Norman said the valve was installed on the waterline to provide for future expansion of the water plant and had been capped at installation.

“The valve blew the cap off the valve where the 36-inch line transitioned to a 20-inch line,” he said.

He said workers removed the valve and replaced it with a blind flange, a round metal plate used to close off ends of pipe systems. He said concrete was poured behind the flange to give it extra support and allowed to cure before turning the system back to the water plant.

The line holding the damaged valve was buried in the ground and under about 10 feet of floodwater, forcing the city to hire contractors to build a dam to wall off the water and allow workers to get in a repair the problem. Flaggs said trucks from “four or five contractors” moved 16,000 to 20,000 cubic feet of dirt over almost 30 hours to build up the dam, which cleared about an acre of land.

He declined to estimate the cost of building the dam and the repair.

He said the city received assistance from the U.S. Army Corps of Engineers Vicksburg District, adding, “The Corps of Engineers came in and said we were doing what we should have been doing. They said the levee was well-built.”

“I think it is remarkable that we had the crisis we had and were able to do it within three days instead of five days,” Flaggs said.

During the outage, the city officials provided bottled water at several locations in the city, and city residents went to spigots owned by the Culkin Water District to get water.

The overuse caused a drop in pressure at Culkin, forcing water district officials to cut of the outside water sources and shut their system down to rebuild pressure to serve water district customers.

Flaggs said the city will reimburse Culkin for the water use.

Flaggs said the city also received donations of water from other cities and businesses, and the city of Jackson which provided the materials to repair the break.

“On behalf of the Board of Mayor and Aldermen, (North Ward) Alderman Michael Mayfield, (South Ward) Alderman Willis Thompson, we cannot begin to thank all the people who have helped us in this crisis situation, certainly the citizens who understood the crisis situation and accommodated and turning to each other instead of turning on each other,” Flaggs said.

About John Surratt

John Surratt is a graduate of Louisiana State University with a degree in general studies. He has worked as an editor, reporter and photographer for newspapers in Louisiana, Mississippi and Alabama. He has been a member of The Vicksburg Post staff since 2011 and covers city government. He and his wife attend St. Paul Catholic Church and he is a member of the Port City Kiwanis Club.